ITEM | PROJECT TITLE | CLIENT | LOCATION | CONSULTANT/CONTRACTOR |
CONTRACT SUM | DURATION | DATE OF COMPLETION | % COMPLETION |
1 | Residential Development |
Mr. Chuks Onyebuchi | Lekki, Scheme 1 | Archi-plus consult Ltd/ Tanimola, Aribisala&co | N65m | 7 Months | 17thJune, 2004 | 100% |
2 | Office Complex |
SON, Lekki | SON, Enugu, Emene. | Archi-plus consult ltd Ltd | N66m | 8 Months | 5th June, 2007 | 100% |
3 | Glass Laboratory |
SON, Lekki | SON, Lekki, Lagos | Archi-plus Consult Ltd |
N38m | 8 Months | 24th Sept, 2008 | 100% |
4 | Office Block (4 Floors) |
GS Micro Finance Bank | Oregun, Ikeja. | Tanimola Aribisala &co | N65m | 6 Months | August 2009 | 100% |
5 | Residential Development |
Mr & Mrs B. Afolabi | VGC, Lagos | Archi-plus Consult Ltd. / Tanimola,Aribisala&co | N60m | 6 Months | November 2009 | 100% |
6 | Block of Flats (7 nos on 4 Floor) |
MultiChoice Development Company, Ikoyi. | Lekki Scheme 1, Lagos | Tanimola Aribisala &co / Archi-plus consult Ltd | N185m | 12 Months | July 2011 | 100% |
7 | Residential Development | Mr. Okojie Odiamenhi | Lekki, Phase 1, Lagos | Archi-plus Consult Ltd | N35m | 6 Months | 18th March, 2001 | 100% |
8 | Residential Development |
Messrs Samvic Ltd |
Lekki, Phase 1, Lagos | Archi-plus Consult Ltd | N40m | 7 Months | 10th, Sept, 2004 | 100% |
9 | Residential Development | Mr. Emmanuel Dick |
VGC, Lagos | Archi-plus Consult Ltd. | N48m | 8 Months | 20th Oct, 2005 | 100% |
10 | Residential Development |
Mr & Mrs Okoro | Arondiziougu, Imo State | Archi-plus Consult Ltd | N50m | 9 Months | 8th Nov, 2005 | 100% |
11 | Residential Development | Capt & Justice (Mrs) Ukeje | Alayi, Abia State | Archi-plus Consult Ltd | N65m | 8 Months | 8 Months | 100% |
12 | Residential Development | Prince Anslem Okoebor | Osborne, Ikoyi, Lagos | Osborne, Ikoyi, Lagos | N55m | 7 Months | 17th June, 2004 | 100% |
13 | Office Complex |
SON, Lekki | SON, Enugu, Emene | Archi-plus Consult Ltd | N66m | 8 Months | 5th June, 2007 | 100% |
14 | Glass Laboratory |
SON, Lekki | Glass Laboratory |
Archi-plus Consult Ltd. | N38m | 8 Months | 24th Sept, 2007 | 100% |
15 | Glass Laboratory |
SON, Lekki | SON, Lekki, Lagos | Archi-plus Consult Ltd | N38m | 8 Months | 24th Sept, 2007 | 100% |
16 | Residential Development |
Dr. A. Ajagu, MFR. | Carlton Gate Estate, Lagos | Archi-plus Consult Ltd. | N200m | 6 Months | July2008 |
100% |
17 | Residential Development |
Mr & Mrs B. Afolabi | VGC, Lagos. | Archi-plus Consult Ltd. | N60m | 41/2 Months | Dec.2009 | 100% |
18 | Residential Development | E.U. Properties Ltd | Carlton Gate Estate, Lagos. | Archi-plus Consult Ltd | N80m | 8 Months | Feb.2010 | 100% |
19 | Residential Development |
Mr. &Mrs Olufemi Ajayi |
NICON TOWN Lekki,, Lagos | Tanimola,Aribisala &co/Archi-plus Consult Ltd . | N 75m | 7 Months | Mar. 2013 | 100% |
20 | Renovation Works | Pastor Tunde Bakare | Kenta, Abeokuta | Kenta, Abeokuta | N13m | 4months | Oct. 2010 | 100% |
21 | Service Station |
Mr. Richard Omojale. | Badore, Ajah. Lagos. | Tanimola,Aribisala& co. | N60m | 61/2 Months | 2014 | 100% |
22 | Renovation Works | Onwards Stationery Stores | Fatai Atere way, Matori. Lagos.. | Tanimola,Aribisala&co. | N18m | 6months | Mar. 2011 | 100% |
23 | Renovation Works-Law office | Mr. A. Agbabiaka | Dolphin Estate. Ikoyi | Tanimola,Aribisala & co | N 15m | 7 Months | Jul.2011 | 100% |
24 | Mechanic Workshop | M/s MEGNOE International ltd | Ifako. Lagos | Tanimola,Aribisala & co./Archi-plus consult ltd | N15m | 4 Months | April 2014 | 100% |
25 | Residential Development | Mr.&Mrs.Clement Oloniruha | Forthright Estate, Magboro | Tanimola,Aribisala&co/Archi-plus Consult Ltd | N35m | 8months | On-going | 85% |
26 | Church Facility | Sureword Assembly, |
Okota, Isolo.Lagos | Tanimola, Aibisala&co | N48m | 9 Months | On- going | |
27 | 60 Bed Hotel |
Chief & Mrs U.Ekwueme | Maiyegun Village, Lekki | Tanimola,Aribisala &co / Archi-plus Consult Ltd | N550m | Ongoing | -------- | 45% |
28 | Intensive Fish Farm | M/S Fdln Ltd |
Oke Alo Village, Gbagada, Lagos. | Archi-plus Consult Ltd / Globond Investment Ltd |
N65m | Ongoing | --------- | 35% |
29 | Residential Development |
Chief & Mrs Tony Chukwu |
Lekki, Phase 1, Lagos | Archi-plus consult Ltd. | N160m | Ongoing | --------- | 45% |